Tag: Working with OEE

OEE Calculation Errors

Database Errors

We agree that collecting and tracking OEE data is a task best suited for a database, however, all the bells and whistles of an OEE system don’t serve much purpose if the calculations are wrong.  Before you make a significant investment in your OEE data collection, tracking, and monitoring system, make sure the system you plan to purchase is calculating the OEE results correctly.

The ultimate system is one that supports automated data collection technology to minimize data entry costs, reduces the risk of entry errors, and provides reporting or monitoring of OEE in real time.  These solutions may be purchased “off the shelf” or customized to your specific process application.

Excel Spreadsheets

If a database is the best approach, you may ask why we use Excel spreadsheets to present our examples or why we supply templates to allow you to track and monitor OEE.  We have four primary reasons:

  1. Almost everyone is familiar with spreadsheets and most people have access to them on their computer.
  2. We determined that a customized database solution being used was not calculating the weighted OEE factors correctly and the overall OEE index was also wrong.  We found it necessary to develop a spreadsheet that made it easy to validate the database calculations.
  3. Database enhancements were easier to develop and demonstrate using a spreadsheet.  We encountered a production process that was equipped with automated data collection capability and provided an overwhelming amount of performance data in real time.  It was easier to perform database queries and use the power of PIVOT tables to develop the desired solutions.
  4. Spreadsheet templates allow you to start collecting and analyzing data immediately.  It also allows the users to get a “feel” for the data.  Although the graphs and drill downs offered by databases are based on predetermined rules, humans are still required to make sense of the data.

Recommendations

In summary, validate the software and its capabilities prior to purchase.  We have observed installations where the OEE data is used to monitor current production performance and the reports generated by the system are used to support the results – good or bad.

We have also evaluated a number of other free OEE spreadsheet offerings on the web and observed that some of these also fail to correctly calculate OEE where multiple machines or part numbers are concerned.  Take a look at our free spreadsheets offerings (see the sidebar).  Our tutorial provides an in depth explanation of how to calculate OEE for single and multiple machines or parts.

The purpose of measuring OEE is to ensure sustained performance with the objective to continually improve over time.  Don’t fall into the trap of setting up a system that, once installed, will only be used to generate reports to justify the current results.

Take the time to train your team and demonstrate how the results will be used to improve their processes.  Involve all of your employees from the very beginning, including the system selection process, so they understand the intent and can provide feedback for what may be meaningful to them while, in turn, they can support the company’s goals and objectives.

Reference Posts.

We encourage you to visit our previous posts showing how to calculate OEE for multiple parts and machines.

  1. Single Process – Multiple Shifts:  OEE

  2. Multiple Parts / Processes:  OEE

  3. Practical OEE

  4. Weighted Calculations:  OEE

  5. How to Calculate OEE

  6. Overall Equipment Efficiency

If you have any questions, comments, or wish to suggest a topic for a future post, please forward an e-mail to leanexecution@gmail.com

We appreciate your feedback.

Until next time – STAY Lean!

OEE and LEAN

Incorporating and tracking performance using Lean metrics doesn’t make a company Lean any more than tracking weight puts you on a diet.  Measurements are like decisions, nothing changes unless actions are taken.

How does this apply to OEE?  How does OEE apply to LEAN?  As we’ve mentioned in previous posts, many companies invest a significant amount of time, money, and effort to develop exorbitant OEE data collection systems.  Data collection and analysis methods are in place, improvement / action plans are developed and executed, and the measurement cycle continues.

To some, this process may appear to be correct.  More formally, a Plan-Do-Check-Act (PDCA) or Define-Measure-Analyze-Improve-Control (DMAIC) process improvement methodology may be used.  So what is wrong with this picture?

OEE Improvements are RELATIVE

OEE does not distinguish between poorly designed and well designed processes.  A poorly designed process may have significant flow constraints and excessive labour but still yield a high OEE index.  The reason for this is simple, the base line or process standards are based on the current known process.  Standard cycle times and quality expectations are based on the current “achievable” performance standards that the process can provide.

Changes to the current process, rates, and quality levels will be reflected in the OEE index.  However, LEAN is not necessarily concerned with effective asset utilization.  The focus of LEAN is to increase or optimize the value added to the product or service being provided while reducing the time required to achieve it.

Implementing OEE is not LEAN

Racing cars and regular street cars may each perform at 100% of their optimum performance levels but clearly they could not compete in a race against each other.  From a LEAN perspective, the racing car will certainly out-perform a regular street car in a head-t0-head speed contest.

Similarly, OEE can provide insight into the performance of the current process, however, it does not provide an indication of how LEAN the process actually is.  A process that is plagued with multiple stations and inherent Work In Progress inventory will never compete against a properly balanced single piece flow process.

The OEE index for any group of processes may be above 85% as defined by design, it doesn’t mean they are equally lean.  Lean should aspire us to achieve a 100% value added process, safely producing the highest quality product in the shortest amount of time.  Although this could never be achieved in the today’s manufacturing environment, VALUE STREAM mapping is the technique used to evaluate our current capabilities in this regard and to determine what a lean future state process could achieve.

So why measure OEE?

OEE measures how effectively an asset or group of assets is being utilized as defined or described by the current standards and process constraints.  Of course, we want to make sure that we are utilizing our assets effectively.  The message here is simple.  Don’t confuse effectiveness with efficiency – they are not the same.

Even efficiency can mean different things to different people.  As we’ve mentioned in previous posts, understand WHAT you are measuring and WHY.  Metrics don’t make a company LEAN although many can help you achieve increasing levels of LEAN.

OEE is an excellent tool to help manage and improve our processes and even more so when the process is optimized using LEAN principles.

The next time someone says they are going LEAN, listen closely.  Usually the statement is met with the typical, “We did 5S and we’re working to improve our OEE.”  The real LEAN practitioner may just share the plan to reduce the cash to cash time and increase or improve the percentage of Value Added activity.

Until Next Time – Stay LEAN

OEE Measurement Error

How many times have you, or someone you know, challenged the measurement process or method used to collect the data because the numbers just “don’t make sense” or “can’t be right”?

It is imperative to have integrity in the data collection process to minimize the effect of phantom improvements through measurement method changes.  Switching from a manual recording system to a completely automated system is a simple example of a data collection method change that will most certainly generate “different” results.

Every measurement system is subject to error including those used to measure and monitor OEE.  We briefly discussed the concept of variance with respect to actual process throughput and, as you may expect from this post, variance also applies to the measurement system.

Process and measurement stability are intertwined.  A reliable data collection / measurement system is required to establish an effective baseline from which to base your OEE improvement efforts.  We have observed very unstable processes with extreme throughput rates from one shift to the next.  We learned that the variance in many cases is not always the process but in the measurement system itself.

We decided to comment briefly on this phenomenon of measurement error for several reasons:

  1. The reporting systems will naturally improve as more attention is given to the data they generate.
  2. Manual data collection and reporting systems are prone to errors in both recording and data input.
  3. Automated data collection systems substantially reduce the risk of errors and improve data accuracy.
  4. Changes in OEE trends may be attributed to data collection technology not real process changes.

Consider the following:

  1. A person records the time of the down time and reset / start up events by reading a clock on the wall.
  2. A person records the time of the down time event using a wrist watch and then records the reset /start up time using the clock on the wall.
  3. A person uses a stop watch to track the duration of a down time event.
  4. Down time and up time event data are collected and retrieved from a fully automated system that instantly records events in real time.

Clearly, each of the above data collection methods will present varying degrees of “error” that will influence the accuracy of the resulting OEE.  The potential measurement error should be a consideration when attempting to quantify improvement efforts.

Measurement and Error Resolution

The technology used will certainly drive the degree of error you may expect to see.  A clock on the wall may yield an error of +/- 1 minute per event versus an automated system that may yield an error of +/- 0.01 seconds.

The resolution of the measurement system becomes even more relevant when we consider the duration of the “event”.  Consider the effect of measurement resolution and potential error for a down time event having a duration of 5 minutes versus 60 minutes.

CAUTION!

A classic fallacy is “inferred accuracy” as demonstrated by the stop watch measurement method.  Times may be recorded to 1/100th of a second suggesting a high degree of precision in the measurement.  Meanwhile, it may take the operator 10 seconds to locate the stop watch, 15 seconds to reset a machine fault, and 20 seconds to document the event on a “report” and another 10 seconds to return the stop watch to its proper location. 

What are we missing?  How significant is the event and was it worth even recording?  What if one operator records the “duration” after the machine is reset while another operator records the “duration” after documenting and returning the watch to its proper location?

The above example demands that we also consider the event type:  “high frequency-short duration” versus “low frequency-long duration” events.  Both must be considered when attempting to understand the results.

The EVENT is the Opportunity

As mentioned in previous posts, we need to understand what we are measuring and why.  The “event” and methods to avoid recurrence must be the focus of the improvement effort.  The cumulative duration of an event will help to focus efforts and prioritize the opportunities for improvement.

Additional metrics to help “understand” various process events include Mean Response Time, Mean Time Between Failures (MTBF), and Mean Time To Repair (MTTR).  Even 911 calls are monitored from the time the call is received.  The response time is as critical, if not more so, than the actual event, especially when the condition is life-threatening or otherwise self-destructive (fire, meltdown).

An interesting metric is the ratio between Response Time and Mean Time To Repair.  The response time is measured from the time the event occurs to the time “help” arrives.  Our experience suggests that significant improvements can be made simply by reducing the response time.

We recommend training and providing employees with the skills needed to be able to respond to “events” in real time.  Waiting 15 minutes for a technician to arrive to reset a machine fault that required only 10 seconds to resolve is clearly an opportunity.

Many facilities actually hire “semi-skilled” labour or “skilled technicians” to operate machines.  They are typically flexible, adaptable, present a strong aptitude for continual improvement, and readily trained to resolve process events in real time.

Conclusion

Measurement systems of any kind are prone to error.  While it is important to understand the significance of measurement error, it should not be the “primary” focus.  We recommend PREVENTION and ELIMINATION of events that impede the ability to produce a quality product at rate.

Regrettably, some companies are more interested in collecting “accurate” data than making real improvements (measuring for measurements sake). 

WHAT are you measuring and WHY?  Do you measure what you can’t control?  We will leave you with these few points to ponder.

Until next time – STAY Lean!

OEE For Dedicated – Single Part – Processes

OEE For Dedicated – Single Part – Processes

Definition: 

Dedicated – Single Part – Process:  A process that produces a single product or slight variations on a theme and does not require significant tooling or equipment changeover events.

A single part process is the easiest application for a OEE pilot project.  The single part process also makes it easier to demonstrate some of the more advanced Lean Thinking tools that can be applied to improve your operation or process.  In our “Variation, Waste, and OEE” post, we introduced the potential impacts of variance to your organization.  We also restated our mission to control, reduce, and eliminate variation in our processes as the primary objective of LEAN.

We need to spend more time understanding what our true production capabilities are.  The single part process makes the process of understanding these principles much easier.  The lessons learned can then be applied to more complex or multipart processes.  In multipart or complex operations, production part sequencing may have a significant impact on hourly rates and overall shift throughput.  How would you know unless you actually had a model that provided the insight?

Process Velocity:  Measuring Throughput

Let’s start this discussion by asking a few simple questions that will help you to get your mind in gear.  Do you measure variation in production output?  Do you measure shift rates?  Do you use the “average” rate per hour to set up your production schedules?  How do you know when normal production rates have been achieved?  Does a high production rate on one shift really signify a process improvement or was it simply a statistically expected event?

Once again an example will best serve our discussion.  Assume the following data represents one week of production over three shifts:

Machine A:  Production Process Performance Report

Cycle Time (Seconds):   57      
Shift Standard (440 minutes) 440      
             
Day Shift Planned Quantity
Production Time Total Test Scrap Accept
Mon 1 440 420 1 2 417
Mon 2 440 390 1 1 388
Mon 3 440 320 1 3 316
Tue 1 440 361 1 1 359
Tue 2 440 392 1 5 386
Tue 3 440 365 1 2 362
Wed 1 440 402 1 7 394
Wed 2 440 317 1 6 310
Wed 3 440 430 1 1 428
Thu 1 440 453 1 5 447
Thu 2 440 419 1 3 415
Thu 3 440 366 1 1 364
Fri 1 440 400 1 2 397
Fri 2 440 411 1 4 406
Fri 3 440 379 1 2 376
Totals 15 6600 5825 15 45 5765

The following table is an extension of the above table and shows the unplanned downtime as well actual, standard, and ideal operating times.

Day Shift Unplanned Operating Time
Down Time Actual Standard Ideal
Mon 1 25 415.0 399.0 396.2
Mon 2 55 385.0 370.5 368.6
Mon 3 122 318.0 304.0 300.2
Tue 1 84 356.0 343.0 341.1
Tue 2 65 375.0 372.4 366.7
Tue 3 82 358.0 346.8 343.9
Wed 1 45 395.0 381.9 374.3
Wed 2 130 310.0 301.2 294.5
Wed 3 30 410.0 408.5 406.6
Thu 1 5 435.0 430.4 424.7
Thu 2 40 400.0 398.1 394.3
Thu 3 90 350.0 347.7 345.8
Fri 1 45 395.0 380.0 377.2
Fri 2 45 395.0 390.5 385.7
Fri 3 60 380.0 360.1 357.2
Totals 15 923 5677 5533.8 5476.8

The table below shows the OEE calculations for each day and shift worked.  Note that this table is also an extension of the above data.

Day Shift Overall Equipment Effectiveness (OEE)
Availability Performance Quality OEE
Mon 1 94.3% 96.1% 99.3% 90.0%
Mon 2 87.5% 96.2% 99.5% 83.8%
Mon 3 72.3% 95.6% 98.8% 68.2%
Tue 1 80.9% 96.3% 99.4% 77.5%
Tue 2 85.2% 99.3% 98.5% 83.3%
Tue 3 81.4% 96.9% 99.2% 78.2%
Wed 1 89.8% 96.7% 98.0% 85.1%
Wed 2 70.5% 97.1% 97.8% 66.9%
Wed 3 93.2% 99.6% 99.5% 92.4%
Thu 1 98.9% 98.9% 98.7% 96.5%
Thu 2 90.9% 99.5% 99.0% 89.6%
Thu 3 79.5% 99.3% 99.5% 78.6%
Fri 1 89.8% 96.2% 99.3% 85.7%
Fri 2 89.8% 98.8% 98.8% 87.7%
Fri 3 86.4% 94.8% 99.2% 81.2%
Totals 15 86.0% 97.5% 99.0% 83.0%

The results from the table above suggest that the process is running just short of world-class OEE (83% versus 90% for dedicated processes.  Note that 85% is considered world-class for multipart variable processes).  As you can see from the daily and shift results, a lot of variation is occurring over the course of the week.  This is the opportunity that we need to pursue further.  A quick scan of the data suggests that Wednesday 2nd shift and Monday 3rd shift are the main contributors to the reduced OEE.  We will investigate the data a little further to really understand what opportunities exist.

A dedicated, continuous process should yield a higher OEE since the process is not subject to continual setup and change over.  Although some model changes or variations to the existing product may exist, they are typically less disruptive.  A OEE of 90% may be an achievable target and is typical for most dedicated operations.

FREE Downloads

We are currently offering our Excel OEE Spreadsheet Templates and example files at no charge.  You can download our files from the ORANGE BOX on the sidebar titled “FREE DOWNLOADS” or click on the FREE Downloads Page.  These files can be used as is and can be easily modified to suit many different manufacturing processes.  There are no hidden files, formulas, or macros and no obligations for the services provided here.

Please forward your questions, comments, or suggestions to LeanExecution@gmail.com.  To request our services for a specific project, please send your inquiries to Vergence.Consulting@gmail.com.

We welcome your feedback and thank you for visiting.

Until Next Time – STAY Lean!

"Click"

Availability and OEE

What is Availability?

In its simplest form, availability measures the uptime of a machine or process against the planned production time.  As one of the factors of Overall Equipment Efficiency (OEE), Availability is expressed as a percentage.  The uptime is calculated by taking the difference between the planned production time and total duration of the downtime events that occurred during the planned production period.

We specifically address the “Availability” factor in this post for the simple reason that the definition of availability is likely to be one of the most debated and hotly contested topics of your OEE implementation strategy.  The reason for this, in many cases, is the lack of clarity in some of the most basic terminology.  The purpose of this discussion is to present some topics for consideration that will allow you to arrive at a clear definition that can perhaps be formed into a standard policy statement.

We will also demonstrate that it is possible to calculate the downtime by simply knowing the cycle time or process rate, the quantity of parts produced, and the planned production time.  We recommend using this technique to validate or reconcile the actual documented downtime.  We would argue that the first and foremost purpose of any machine monitoring or downtime event measurement system is to determine the “WHY and WHAT” of the downtime events and secondly to record the “When and How Long”.

You will learn that monitoring your processes to determine causes and duration of downtime events  is key to developing effective action plans to improve availability.  The objective of any machine automation, sensor strategy, or data collection and analysis is to determine methods and actions that will improve the availability of the equipment through permanent corrective actions, implementing more effective trouble shooting strategies (sensor technologies), improved core process controls, or more effective preventive maintenance.

Define the purpose of OEE

While it looks like we’re taking a step back from the topic of discussion, bear with us for just a paragraph or two.  A clear statement of purpose is the best place to start before executing your OEE implementation strategy:

To identify opportunities to improve the effectiveness of the company’s assets.

You will quickly realize that, when attempting to define the measurement criteria for the OEE factors, in particular Availability, your team may present rationale to exclude certain elements from the measurement process.  These rationalizations are typically predicated on existing policy or perceived constraints that simply cannot be changed.  People or teams do not want to be penalized for items that are “out of their control” or bound by current policy.  Continuous improvement is impeded by attempts to rationalize poor performance.

We understand that some of these “exclusions” present a greater challenge, however, we do not agree with the premise that they cannot be improved.  Again, it is a matter of “purpose”.  Limiting the scope of measurement will limit the scope of improvement.  Now it’s time to explore what could be the foundation for a sound definition of availability.

Availability Considerations

It may seem reasonable to assume that, at a minimum, the only planned down time events that should be excluded from the availability factor are  planned preventive maintenance activities, mandatory break periods, and scheduled “down” time due to lack of work.  We would argue and agree that the only justification for an idle machine is “Lack of Work”.

What would be the reason to settle for anything less?  If Preventive Maintenance is critical to sustaining the performance of your process, doesn’t it make sense to consider it in the measurement process?  The rationale that typically follows is that Preventive Maintenance must be done and it’s really out of our control – it is a planned event.  We would argue that the time to complete Preventive Maintenance can be improved.

Is it possible that the Mean Time Before Failure or Required Maintenance can be extended?  Is it possible to improve materials, components, or lubricants that could extend the process up time?  Is it possible to improve the time it actually takes to perform the required maintenance?  If so, what is the measure that will be used to show that additional capacity is available for production.

If set up times for die changes or tool changes can be improved from hours to minutes, could the same effort and devotion to improve Preventive Maintenance techniques yield similar results?  We think so.

One example is the use of synthetic oils and lubricants that have been proven to significantly extend the life of tools and components and also reduces the number changes required over the service life of the machine.  Quick change features that can assist with easy and ready access to service points on tooling and machines can also be implemented to reduce preventive maintenance times.

The other exclusion that is often argued is break times.  Labour laws require you to provide break times for your employees.  However, since automated processes are not subject to “Labour Laws”, the “mandatory break times” do not apply.  We would argue that methods should be pursued to reduce the need for human intervention and look for ways to keep the machine running.  Is it possible to automate some of the current processes or rotate people to keep the machine running?

Aside from this more obvious example, consider other organizational policies that may impact how your organization runs:

  1. Shift start-up meetings
  2. Employee Communication Meetings
  3. End of Shift clean up periods
  4. Quality first off approval process
  5. Shift first off versus Run first off
  6. Weld Tip changes – PM or Process Driven

 What is the purpose of the shift start-up meeting?  What is the purpose of the monthly employee communication meeting?  Could this information be conveyed in a different form?  What length of time is really required to convey the message to be shared?  Is the duration of the meeting actually measured or do you resort to the standard time allotted?

Clean up periods at the end of the shift  are also a common practice in many plants.  What is being cleaned up?  Why?  Is it possible to maintain an orderly workplace during the shift – clean up as it happens in real-time?  Again, do you record the actual clean up time or do you just enter the default clean up time allotted?

How much time is lost to verify the integrity of the product before allowing production to commence?  What process parameters or factors would jeopardize the quality of the product being produced?  No one wants to make scrap or substandard components, however, the challenge remains to determine what factors influence the level of quality.  If it is possible to determine what factors are critical to success in advance, then perhaps the quality verification process becomes a concurrent event.

Measuring Downtime.

 There are other factors that can impact availability including, but certainly not limited to, personnel (illness, inclement weather), material availability, other linked processes (feeder / customer), material changes, tool changes, quality concerns, and unexpected process, equipment, or machine faults.

It is possible to use manual or automated systems to collect various machine or process codes to record or document the duration and type of downtime event.  We recommend and support the use of automated data collection systems, however, they should be implemented in moderation.  One of the primary impediments to success is overwhelming volumes of data that no one has the time to analyze.

The Goal = 100% Up Time = ZERO Down Time = Zero Lost Time = Zero Defects = 100% Availability

The goal is to use the data and tools available to either permanently resolve the problem by implementing an effective corrective action or to assist the trouble shooting process by identifying the failure mode and to minimize the duration of the downtime event.

We have witnessed data collection strategies where an incredible number of sensors were installed to “catch” problems as they occur.  The reality was the sensors themselves became the greater cause of downtime due to wear or premature failure due to improper sensor selection for the application.  Be careful and choose wisely.

When used correctly, automation can be a very effective tool to capture downtime events and maintain the integrity of the overall measurement process.  With the right tools, trouble shooting your process will minimize the duration of the down time event.  Monitoring the frequency of these events will also allow you to focus your attention on real opportunities and circumvent nuisance faults.

The objective of collecting the “downtime event” history is to determine what opportunities are available to improve uptime.

Duration versus Frequency

The frequency of a downtime event is often overlooked as most of the attention is devoted to high duration downtime events.  Some sources suggest that short duration downtime events (perhaps as little as 30 seconds) are not worth measuring.  These undocumented losses are reflected, or more accurately hidden, by a corresponding reduction in the performance factor.

Be careful when setting what appears to be simple policy to document downtime.  A 20 second downtime event that occurs 4 times per hour could quickly turn into 10 minutes a shift, 30 minutes a day, 2.5 hours a week, 125 hours a year.  Rather than recording every event in detail, we recommend implementing a simple “tick” sheet to gain an appreciation for the frequency of failures.  Any repetitive events can be studies and reviewed for corrective action.

Verify the Downtime

One of the advantages of OEE is that it is possible to reconcile the total time – OEE should never be greater than 100%.  Of course this statement requires that the standard cycle time is correct and the total quantity of parts produced is accurate.  So, although all of the downtime events may not be recorded, it is very easy to determine how much downtime occurred.  This will help to determine how effectively downtime data is being recorded.

A perfect example to demonstrate this comes from the metal stamping industry.  Progressive dies are used to produce steel parts from coil steel.  The presses typically run at a fixed “predetermined” optimum run rate.  Depending on the type of part and press, progressive dies are capable running at speeds from as low as 10 strokes per minute up to speeds over 300 strokes per minute.

For ease of calculation, assume we have a press that was scheduled to run a part over an 8 hour shift having two 10 minute breaks.  The standard shift hours are 6:45 am – 3:15 pm and 3:30 pm – 12:00 am.  The company provides a 30 minute unpaid meal break after 4 hours of work.  The optimum press speed to run the part is 20 strokes per minute (spm).  If a total of 6200 parts were made – how much downtime was incurred at the press?

To determine the press time required (also known as earned time), we simply divide the quantity of parts produced by the press rate as follows:

Machine Uptime:  6200 / 20 = 310 minutes

Our planned production time was 8 hours or 480 minutes.  Assuming that company policy excludes break times, the net available time to run the press is 480 – (2 x 10) = 460 minutes.

Calculated downtime = Available – Earned = 460 – 310 =150 minutes

Availability = Earned Time / Net Available Time = 310 / 460 = 67.39%

We can see from the above example that it easy to determine what the downtime should have been and, in turn, we could calculate the availability factor.  This calculation is based on the assumption that the machine is running at the stated rate.

The Availability TWIST (1):

Knowing that press and die protection technologies exist to allow presses to run in full automatic mode, the two break periods from our example above do not apply to the equipment, unless company policy states that all machines or processes must cease operations during break periods.

Assuming that this is not the case, the press is available for the entire shift of 480 minutes.  Therefore, the availability calculations from above would be:

Calculated downtime = Available – Earned = 480 – 310 =170 minutes

Availability = Earned Time / Net Available Time = 310 / 480 = 64.58%

The Availability TWIST (2):

Just to expand on this concept just a little further.  We also indicated that the company provided an unpaid lunch period of 30 minutes.  Since meal breaks don’t apply to presses, the reality is that the press was also available to run during this period of time.  The recalculated downtime and availability are:

Calculated downtime = Available – Earned = (480 + 30) – 310 =200 minutes

Availability = Earned Time / Net Available Time = 310 / 510 = 60.78%

The Availability TWIST (3):

Finally, one last twist (we could go on).  We deliberately indicated that there was a 15 minute break between shifts.  Again, is there a reason for this?  Does the machine have to stop?  Why?

Availability – NEXT Steps

As you begin to look at your operations and policies, start by asking WHY do we do this or that?  The example provided above indicates that a significant delta can exist in availability (close to 7%) although the number of parts produced has not changed.  The differing results are related to policy, operating standard, or both.

If the performance (cycle time or production rate) and total quantity of parts produced data have integrity, the availability factor can be reconciled to determine the integrity of the downtime “data collection” system.  From this example it should also be clear that the task of the data collection system is to capture the downtime history as accurately as possible to determine the opportunities to improve availability NOT just to determine how much downtime occurred.

This example also demonstrates why effective problem solving skills are critical to the success of your lean implementation strategy and is also one of the reasons why programs such as six sigma and lean have become integrated as parallel components of many lean execution strategies.

The Goal:  100% uptime / Zero downtime / Zero lost time /100% availability

Regardless of the measurement baseline used, be consistent.  Exclusions are not the issue, it is a matter of understanding what is involved in the measurement process.  For example, maintenance activities performed during break periods may be a good management practice to improve labour efficiencies, however, the fact that the work was performed during a break period should not exclude it from the “downtime” event history.  We would argue that all activities requiring “equipment time” or “process time” should be recorded.

FREE Downloads

We are currently offering our Excel OEE Spreadsheet Templates and example files at no charge.  You can download our files from the ORANGE BOX on the sidebar titled “FREE DOWNLOADS” or click on the FREE Downloads Page.  These files can be used as is and can be easily modified to suit many different manufacturing processes.  There are no hidden files, formulas, or macros and no obligations for the services provided here.

Please forward your questions, comments, or suggestions to LeanExecution@gmail.com.  To request our services for a specific project, please send your inquiries to Vergence.Consulting@gmail.com.

We welcome your feedback and thank you for visiting.

Until Next Time – STAY Lean!

"Click"

Variance, Waste, and OEE

What gets managed MUST be measured – Including VARIANCE.

It is easy to get excited about the many opportunities that a well implemented LEAN Strategy can bring to your organization.  Even more exciting are the results.

Achieving improvement objectives implies that some form of measurement process exists – the proof.  A clear link should be established to the metric you choose and the activity being managed to support the ongoing improvement initiatives.

Measure with Meaning

Why are you “collecting” OEE data?  While OEE can and should be used to measure the effectiveness of your manufacturing operations, OEE on its own does not present a complete solution.  It is true that OEE presents a single metric that serves as an indicator of performance, however, it does not provide any insight with respect to VARIANCES that are or may be present in the system.

We have encountered numerous operations where OEE data can be very misleading.  OEE data can be calculated using various measurement categories:  by machine, part number, shift, employee, supervisor, department, day, month, and so on.

VARIANCE:  the leading cause of waste!

Quality professionals are more than familiar with variance.  Statistically capable processes are every quality managers dream.  Unfortunately, very little attention or focus is applied to variances experienced on the production side of the business.

Some may be reading this and wonder where this is going.  The answer is simple, rates of production are subject to variance.  Quite simply, if you review the individual OEE results of any machine for each run over an extended period of time, you will notice that the number is not a constant.  The performance, availability, and quality factors are all different from one run to the next.  One run may experience more downtime than another, a sluggish machine may result in reduced in performance, or material problems may be giving rise to increased quality failures (scrap).

So, while the OEE trend may show improvement over time, it is clear that variances are present in the process.  Quality professionals readily understand the link between process variation and product quality.  Similarly, variation in process rates and equipment reliability factors affect the OEE for a given machine.

We recommend performing a statistical analysis of the raw data for each factor that comprises OEE (Availability, Performance, and Quality) for individual processes.  Analysis of OEE itself requires an understanding of the underlying factors.  It is impractical to consider the application of ANOVA to OEE itself as the goal is to continually improve.

How much easier would it be if you could schedule a machine to run parts and know that you will get them when you needed them?  You can’t skip the process deep dive.  You need to understand how each process affects the overall top-level OEE index that is performance so you can develop and implement specific improvement actions.

The best demonstration we have seen that illustrates how process variation impacts your operation is presented through a “process simulation” developed from Eli Goldratt’s book, The Goal.  We will share this simulation in a separate post.  Experiencing the effect of process variation is much more meaningful and memorable than a spreadsheet full of numbers.

Conflict Management and OEE

In some environments we have encountered, the interpretation of LEAN strategy at the shop floor level is to set minimum OEE performance objectives with punitive consequences.  This type of strategy is certainly in conflict with any Lean initiative.  The lean objective is to learn as much as possible from the process and to identify opportunities for continual improvement.

Management by intimidation is becoming more of a rarity, however, we have found that they also give rise to the OEE genius.  If performance is measured daily, the OEE genius will make sure a high performing job is part of the mix to improve the “overall” result.  This is akin to taking an easy course of study to “pull up” your overall average.

It is clear from this example, that you will miss opportunities to improve your operation if the culture is tainted by conflicting performance objectives.  The objective is to reveal sources of variation to eliminate waste and variation in your process, not find better ways to hide it.

Variance in daily output rates are normal.  How much are you willing to accept?  Do you know what normal is?  Understanding process variance and OEE as complementary metrics will surely help to identify more opportunities for improvement.

FREE Downloads

We are currently offering our Excel OEE Spreadsheet Templates and example files at no charge.  You can download our files from the ORANGE BOX on the sidebar titled “FREE DOWNLOADS” or click on the FREE Downloads Page.  These files can be used as is and can be easily modified to suit many different manufacturing processes.  There are no hidden files, formulas, or macros and no obligations for the services provided here.

Please forward your questions, comments, or suggestions to LeanExecution@gmail.com.  To request our services for a specific project, please send your inquiries to Vergence.Consulting@gmail.com.

We welcome your feedback and thank you for visiting.

Until Next Time – STAY Lean!

"Click"

Problem Solving with OEE – Measuring Success

OEE in Perspective

As mentioned in our previous posts, OEE is a terrific metric for measuring and monitoring ongoing performance in your operation.  However, like many metrics, it can become the focus rather than the gage of performance it is intended to be.

The objective of measuring OEE is to identify opportunities where improvements can be made or to determine whether the changes to your process provided the results you were seeking to achieve.  Lean organizations predict performance expectations and document the reasons to support the anticipated results .  The measurement system used to monitor performance serves as a gauge to determine whether the reasons for the actual outcomes were valid.  A “miss” to target indicates that something is wrong with the reasoning – whether the result is positive or negative.

Lean organizations are learning continually and recognize the need to understand why and how processes work.  Predicting results with supported documentation verifies the level of understanding of the process itself.  Failing to predict the result is an indicator that the process is not yet fully understood.

Problem Solving with OEE

Improvement strategies that are driven by OEE should cause the focus to shift to specific elements or areas in your operation such as reduction in tool change-over or setup time, improved material handling strategies, or quality improvement initiatives.  Focusing on the basic tenets of Lean will ultimately lead to improvements in OEE.  See the process in operation (first-hand), identify opportunities for improvement, immediately resolve,  implement and document corrective actions, then share the knowledge with the team and the company.

Understanding and Managing Variance:

OEE data is subject to variation like any other process in your operation.  What are the sources of variation?  If there is a constant effort to improve performance, then you would expect to see positive performance trends.  However, monitoring OEE and attempting to maintain positive performance trends can be a real challenge if the variances are left unchecked.

Availability

What if change-over times or setup times have been dramatically reduced?  Rather than setting a job to run once a week, it has now been decided to run it daily (five times per week).  What if the total downtime was the same to make the same number of parts over the same period of time?  Did we make an improvement?

The availability factor may very well be the same.  We would suggest that, yes, a signficant improvement was made.  While the OEE may remain the same, the inventory turns may increase substantially and certainly the inventory on hand could be converted into sales much more readily.  So, the improvement will ultimately be measured by a different metric.

Performance

Cycle time reductions are typically used to demonstrate improvements in the reported OEE.  In some cases, methods have been changed to improve the throughput of the process, in other cases the process was never optimized from the start.  In other instances, parts are run on a different and faster machine resulting in higher rates of production.  The latter case does not necessarily mean the OEE has improved since the base line used to measure it has changed.

Quality

Another example pertains to manual operations ultimately controlled through human effort.  The standard cycle time for calculating OEE is based on one operator running the machine.  In an effort to improve productivity, a second operator is added.  The performance factor of the operation may improve, however, the conditions have changed.  The perceived OEE improvement may not be an improvement at all.  Another metric such as Labour Variance or Efficiency may actually show a decline.

Another perceived improvement pertains to Quality.  Hopefully there aren’t to many examples like this one – changing the acceptance criteria to allow more parts to pass as acceptable, fit for function, or saleable product (although it is possible that the original standards were too high).

Standards

Changing standards is not the same as changing the process.  Consider another more obvious example pertaining to availability.  Assume the change over time for a process is 3o minutes and the total planned production time is 1 hour (including change over time).  For simplicity of the calculation no other downtime is assumed.  The availability in this case is 50% ((60 – 30) / 60).

To “improve” the availability we could have run for another hour and the resulting availability would be 75% (120 – 30) / 120.  The availability will show an improvement but the change-over process itself has not changed.  This is clearly an example of time management, perhaps even inventory control, not process change.

This last example also demonstrates why comparing shifts may be compromised when using OEE as a stand-alone metric.  What if one shift completed the setup in 20 minutes and could only run for 30 minutes before the shift was over (Availability = 60%).  The next shift comes in and runs for 8 hours without incident or down time (Availability = 100%).  Which shift really did a better job all other factors being equal?

Caution

When working with OEE, be careful how the results are used and certainly consider how the results could be compromised if the culture has not adopted the real meaning of Lean Thinking.  The metric is there to help you improve your operation – not figure out ways to beat the system!

FREE Downloads

We are currently offering our Excel OEE Spreadsheet Templates and example files at no charge.  You can download our files from the ORANGE BOX on the sidebar titled “FREE DOWNLOADS” or click on the FREE Downloads Page.  These files can be used as is and can be easily modified to suit many different manufacturing processes.  There are no hidden files, formulas, or macros and no obligations for the services provided here.

Please forward your questions, comments, or suggestions to LeanExecution@gmail.com.  To request our services for a specific project, please send your inquiries to Vergence.Consulting@gmail.com.

We welcome your feedback and thank you for visiting.

Until Next Time – STAY Lean!

"Click"

OEE for Multiple Parts – Single Machine (Multipart Processes)

How to Calculate OEE for Single Machine and Multiple Parts.

Flexible manufacturing provides the advantage of producing many different parts on the same piece of equipment.  The same is true for processes such as stamping presses, molding machines, or machining operations.

The first question most often asked is, “How do we calculate OEE for a piece of equipment that is capable of manufacturing multiple parts?”  The overall OEE for a stamping press, molding machine, machining process, or other “multipart” process is easily calculated using the same formulas presented in our previous posts “How to Calculate OEE” and “Practical OEE“.

We presented three machines running at various rates and producing unique products.  We demonstrated how to calculate the OEE for each part individually and for all parts collectively.  The machines A, B, and C could very easily be parts A, B, and C running on one machine.  The application of the OEE formulas presented for these three machines is the same for multiple parts running on the same machine.

We have prepared two Excel spreadsheets that demonstrate how to calculate OEE for a single machine that produces multiple parts.  We have also created a separate Excel spreadsheet that will show you how to calculate OEE for Multiple Departments and Multiple Machines running Multiple Parts.

Calculating OEE for any period of time, department, or group of equipment is a simple task.  With the understanding that OEE measures how effectively Net Available Time is used to produce good parts at the ideal rate, the formula for any OEE calculation follows:

OEE (Any Category) = Total SUM of IDEAL Time / Total SUM of NET Available Time

Once this basic premise for OEE calculations is clearly understood, any combination of OEE summaries can be prepared including OEE summaries by Shift, Operator, Manager, Division, Process, and Process Type.

FREE Downloads 

We are currently offering our Excel OEE Spreadsheet Templates and example files at no charge.  You can download our files from the ORANGE BOX on the sidebar titled “FREE DOWNLOADS” or click on the FREE Downloads Page.  These files can be used as is and can be easily modified to suit many different manufacturing processes.  There are no hidden files, formulas, or macros and no obligations for the services provided here.

Multipart OEE – Confronting the Challenges

Most manufacturing environments are challenged with the task of minimizing inventories requiring more frequent change-overs or setups.  By far, the greatest challenge of multipart equipment is managing the change-over process and is usually reflected in the OEE Availability factor.

We recommend including setup or change-over time as part of the unplanned downtime calculation.  Then, by definition, one method to improve Availability is to reduce change-over or setup time.  Reductions in change-over time will also be reflected by improved Availability.  The Availability factor is now a useful metric for tracking improvements.

According to our definition, change-over time or setup time is measured from the end of the current production run (“the last good part made”) to the start of the next production run (“first good part produced”).  We have worked with some manufacturers that decided to do change-overs on the off shift so that they could avoid the down time penalty.  They clearly didn’t get the point – deferring the time when the change-over is performed doesn’t change the time required to perform it.

Several programs such as SMED (single minute exchange of dies) are available and, when coupled with best practices for quick die change (QDC) or quick tool change techniques, can greatly reduce the time lost during your tool change events.

We will consider posting best practices for SMED or QDC and would welcome any reader comments in this area.

We always welcome your feedback and comments.  Feel free to send us your questions or comments to leanexecution@gmail.com

Until Next Time – STAY Lean!